Saudis Seek Up to $50 Billion in Renewable-Energy Expansion

Saudi Arabia will start soliciting bids in the next few weeks for the first phase of a “massive” renewable-energy program costing $30 billion to $50 billion, Energy Minister Khalid Al-Falih said.

OPEC’s biggest producer plans to generate close to 10 gigawatts from renewables, primarily solar and wind power, by 2023, he said at an energy conference in Abu Dhabi. The first tender may be for 700 megawatts of capacity at a cost of about $700 million, according to Roberto de Diego Arozamena, chief executive officer of Saudi power developer Abdul Latif Jameel Energy, which plans to bid for the contract.

Saudi Arabia plans by 2030 to produce 70 percent of its power from natural gas and 30 percent from renewables and other sources, Al-Falih said Monday. He didn’t say how much renewables capacity the nation would be tendering in coming weeks.

The kingdom is among crude exporters struggling with budget deficits after oil prices languished for two years at about $50 a barrel. Building more solar plants and developing a nuclear-power industry is part of a broader plan that Deputy Crown Prince Mohammed bin Salman announced in April to diversify the economy away from crude sales as the main source of government income.

The goal of 10 gigawatts is “only the beginning,” Al-Falih said. “I’m not able to give you the number of where we will be in 2050.”

Nuclear Plans

The goals for renewables boosting capacity over the next seven years are achievable, and the start of the tender process is a sign Saudi Arabia is serious about reaching them, de Diego Arozamena said Tuesday in an interview in Abu Dhabi.

Saudi Arabia is also “really moving” to develop nuclear power and intends to build two reactors with a combined capacity of 2.8 gigawatts, Al-Falih said. The country is currently in the front-end engineering and design stage of its nuclear plants, he said. He didn’t say when the nuclear plants would be operational.

The country’s only solar plant in operation, aside from a smaller pilot project, is a 10-megawatt facility on top of a parking lot at the headquarters of state-owned Saudi Arabian Oil Co., known as Saudi Aramco. The national utility, Saudi Electricity Co., is seeking bids for two plants to generate a combined 100 megawatts.

Saudi Arabia previously had longer-term targets for renewable power when crude prices were about double their current level. Its earlier solar program forecast more than $100 billion of investment in projects to produce 41 gigawatts of power by 2040. In January 2015, the government delayed the deadline for meeting that capacity goal by nearly a decade, saying it needed more time to assess the relevant technologies.

The current Saudi solar program is viable, said Francesco Starace, chief executive officer of Italian utility Enel SpA, which wants to participate in renewables projects there. Saudi Arabia “has no problem in attracting financing provided that basic rules are well-defined,” he said Saturday in an interview in Abu Dhabi.

About BloombergNEF

BloombergNEF (BNEF) is a strategic research provider covering global commodity markets and the disruptive technologies driving the transition to a low-carbon economy. Our expert coverage assesses pathways for the power, transport, industry, buildings and agriculture sectors to adapt to the energy transition. We help commodity trading, corporate strategy, finance and policy professionals navigate change and generate opportunities.
 
Sign up for our free monthly newsletter →

Want to learn how we help our clients put it all together? Contact us